It’s really amazing when we discover God’s provision! On July 24th, we signed a letter of intent with Flory Construction, bringing us one step closer in the hiring this company as our G/C. I know many of us have been praying for the building project. More specifically, praying for a Christian, a Church Builder, who we can together built this building for His Kingdom. God answer our prayers. He knows our every needs. Let us praise Him, He is Lord, He blesses those who seek Him on all things.
It was approx. six weeks ago, while we were busy talking to the design team to correct columns misalignment, the architect informed the church that one column at the southeast corner was omitted on the architectural drawing. We also learned that one parking stall has quickly disappeared in favor of the missing column. What could be worse? The Architect informed us we must move the building approx. 2 ft to the north, as the new column encroaches onto Santa Clara Water District’s easement. Working to resolve some of the issues pertaining to moving the building, the Architect informed us that we can rotate the building counter-clock slightly and by doing so, we don’t need to move the building northerly by 2 ft. In addition, we can recover one parking stall next to the newly added column. These solutions were worthy of our praise and thanksgiving to our God.
While we were working together on resolving some of the outstanding issues, the high cost of trenching for the underground utilities was before us. We met with the PG&E representative to discuss possibly relocate the power transformer to the front of the building and closer to the power pole from across the street. In essence, this move will reduce the trenching and underground construction cost. The PG&E representative agreed with our suggestion. As such, our Architect was able to incorporated all the above changes: adding the missing column, rotate the building to avoid the easement, relocate the transformer pad to the front of the building on to the revised drawing. Three complete sets of drawings were submitted to the SJ Examiner for review on Monday 8/6/2007. Although some of these changes were insignificant, but none-the-less, the re-submittal was required. Please continue to pray that no negative comments will come from SJ Examiner on the revised drawing.
During our initial meeting with Flory Construction, David suggested a reduced fire rated building will lower the construction cost. We proceeded to talk with our architect. Meetings were held between our Architect and SJ Examiner to review the building code, occupancy and area analysis to determine whether reduced fire rating is applicable. Architect informed us that our request was denied. Two weeks ago, our Architect, Ming Ng and I met with the SJ Examiner, his manager, and a representative from the Fire Dept. to review our change request. We learned it was possible to change the occupancy on the ground floor. However, the fact that we have classrooms on the second floor, the building code for fire requires us to be Type V - 1 hour rating throughout the entire building. At the conclusion of our meeting, we decided to not change our occupancy and keep the building as originally designed.
A few days after our meeting with SJ Examiner, he wrote us a letter, appraising us the attic-storage has been declared unusable. This was a shocking surprise to all of us, including the architect. The Architect corresponded with SJ Examiner, quoting the building code and provided substantial justification on the attic-storage for church use. Given the documented support, SJ Examiner concurred with the Architect and reinstated the attic-storage for church use. Hallelujah, hallelujah, praise Him!
Last week, AMStar informed us in writing that the steel delivery has been postponed to the week ending October 19th. However, we may request for a partial delivery of structural steel and roof in September. We plan to discuss the building construction schedule with Flory Construction this week. Once we determine the best schedule for our project, we will request for the steel delivery accordingly.
Please pray for the following:
1. completion of our grading,
2. completion of the building pad,
3. agreement to hire G/C David Flory
4. start the underground construction
5. start the foundation
6. schedule the steel delivery
7. delay the rainy season
Please reserve Sat. September 29 on your calender. You are invited to a celebration dinner on the construction milestone and the sharing of the church building vision.
William